Second Belgian mine counter-measure ship launched
Tournai is the third mine countermeasure vessel of the Belgian-Dutch remote mine countermeasure (rMCM) programme. (Photo: Naval Group)
The Belgian Navy’s second new mine countermeasure ship, Tournai, was launched on 2 July with an expectation that it will be delivered in 2026.
Tournai is the third of the twelve mine countermeasure vessels in the Belgian-Dutch rMCM programme. The first ship in the series, Oostende, destined for the Belgian Navy, was launched on 29 March 2023. The second, Vlissingen, destined for the Royal Netherlands Navy, was launched on 19 October 2023.
The fourth in the series, Scheveningen, the second vessel for the Dutch Navy, was laid down on 19 July 2023 and is scheduled to be launched in December 2024.
Related Articles
rMCM launch and recovery system undergoes tests
First Belgian-Dutch rMCM vessel launched
Dutch navy launches new rMCM vessel
Delivery of Oostende is scheduled for summer 2025 in Zeebrugge, Belgium. Deliveries of the other ships will then be staggered until mid-2030, at a rate of two a year.
In September 2023, a Memorandum of Understanding (MoU) was signed between France, Belgium and the Netherlands, allowing France to use the design of the rMCM ships to equip the French Navy with six ships.
France’s Naval Group is overall architect and prime contractor and responsible for the design of the ships, overall integration, testing and commissioning of the mission system (combat system and mine countermeasures system).
Kership, a joint venture between Naval Group and Piriou, is the industrial prime contractor for the 12 ships, which are being built in Concarneau and Lanester.
The main strength of the ships is what Naval Group refers to as “the toolbox” which consist of the capacity to operate surface uncrewed surface vessels (vessels of around 12m and 18t), underwater uncrewed systems and UAS.
Related Equipment in Defence Insight
More from Naval Warfare
-
Avalon 2025: Kongsberg confirms its first Australian missile factory
The deal, which has been planned since August 2024, is part of an ongoing attempt to bolster Australia’s defences against the potential of Chinese aggression.
-
As Australian resistance rises, is AUKUS in trouble?
The tripartite submarine project is under political pressure from a grass-roots Australian Labor Party movement, but it could also have practical issues in its way.
-
Newest Arleigh Burke Flight III destroyer launched and ready for fitting
DDG 129, which will become the USS Jeremiah Denton on commissioning, was moved to dry dock to begin its technical fitting and testing.