New French support ship Jacques Chevallier hits the water
On 29 April, Saint-Nazaire shipyard Chantiers de L’Atlantique launched the first of four new Bâtiments Ravitailleurs de Force (BRF) support ships Jacques Chevallier under the country’s FLOTLOG programme.
The launch follows a record 50-day assembly from the arrival of the first section in December 2021 to the laying of the final block in March.
Chantiers de l'Atlantique GM Laurent Castaing said the assembly of the 20 blocks in just 50 days demonstrated the Saint-Nazaire shipyard's expertise 'as manufacturer of civilian ships can greatly benefit the military in terms of time, cost and quality control.'
Chantiers de l'Atlantique and Naval Group
Already have an account? Log in
Want to keep reading this article?
Read this Article
Get access to this article with a Free Basic Account
- Original curated content, daily across air, land and naval domains
- 2 free stories per week
- Personalised news alerts
- Daily and weekly newsletters
Unlimited Access
Access to all our premium news as a Premium News 365 Member. Corporate subscriptions available.
- Original curated content, daily across air, land and naval domains
- 14-day free trial (cancel at any time)
- Unlimited access to all published premium news
More from Naval Warfare
-
Austal completes autonomy trials with former Royal Australian Navy patrol boat
The work took place under the Patrol Boat Autonomy Trial (PBAT), which has been a collaboration between Austal, Greenroom Robotics, the Trusted Autonomous Systems Defence Cooperative Research Centre and the Royal Australian Navy’s (RAN) Warfare Innovation Navy Branch.
-
Singapore launches fourth and final Type 218SG submarine
The era of southeast Asian submarine modernisation has been in full swing fuelled by growing tensions in the South China Sea.
-
Keel laid for third Hellenic Navy frigate as harbour trials start for first
On 24 March 2022, Greece and Naval Group have signed a contract for three defence and intervention (FDI) frigates. Two warships will be due for delivery in 2025 and the third expected the following year, with the deal including an option to add a fourth frigate to be ready in 2027.