Malaysia considers whether to stick or twist with LCS
The Malaysian Ministry of Defence (MINDEF) is mulling how to proceed with its troubled Maharaja Lela -class Littoral Combat Ship (LCS) programme.
None of the six LCS vessels on order from Boustead Naval Shipyard have been successfully completed, Defence Minister Datuk Seri Ismail Sabri Yaacob told parliament on 3 August.
LCS 1 is almost 60% completed, ahead of LCS 2 (48%), LCS 3 (43.75%), LCS 4 (36.49%) and LCS 5 (20%). Construction of LCS 6 is yet to begin.
This means that the overall programme is some 31 months behind schedule, Ismail Sabri said, and costs are spiralling beyond the original MYR9.13 billion ($2.16 billion) contract ceiling.
The LCS project faces a Cabinet-level review, with three options in play.
‘The first option is for the project to be continued by appointing Naval Group France as a rescue contractor… using the remaining contract ceiling to complete at least two LCS units,’ Ismail Sabri said.
Alternatively, Boustead Naval Shipyard would be required to complete ‘at least two LCS units’ within the remaining contract ceiling, he added.
The third option is to terminate the contract entirely, with the government stepping in the save the LCS programme.
Ismail Sabri said that saying that MINDEF does not intend to inject additional funds for Bousted Naval Shipyard to complete the LCS programme, despite a request from the shipbuilder.
However, the government could pay for the design rights and complete construction itself.
As part of our promise to deliver comprehensive coverage to our Defence Insight and Premium News subscribers, our curated defence news content provides the latest industry updates, contract awards and programme milestones.
Related Programmes in Defence Insight
Littoral Combat Ship Programme (1-5) [Malaysia]
Related Equipment in Defence Insight
More from Naval Warfare
-
US Coast Guard orders 10 additional Fast Response Cutters
The USCG exercised a $507 million contract option for the acquisition of 10 extra FRCs. This new order will raise the total number of Sentinel-class vessels procured by the service from 67 to 77.
-
DSEI 2025: Red Cat expands into USV production with focus on combat-proven technology
At DSEI 2025, Red Cat outlines its expansion from UAVs into uncrewed surface vessels (USVs), positioning itself as a multi-domain defence provider spanning land, sea, and air.
-
Anduril Australia wins A$1.7 billion Ghost Shark XL-AUV contract
The vessels are expected to deliver a major boost to Australia’s undersea warfare capabilities, with production set to start immediately.
-
Royal Canadian Navy will start operating class 2 UAVs in 2028
Acquired under Canada’s Department of National Defence ISTAR UAS project, the drones will be deployed from the Halifax-class frigates.