ANAO highlights Australian procurement woes
The MRH90 has been listed as a ‘project of concern’ since 2011. (ADF)
The Australian Department of Defence continues to experience difficulties in delivering major procurement projects.
This is despite a fall in the total number of months of project slippage recorded by the Australian National Audit Office (ANAO) across 21 major projects: it was 405 months in 2020-21, down from 507 in 2019-20.
The ANAO’s Major Projects Report (MPR) 2020-21, released in mid-December 2021, stated that this reduction was largely because a large number of late projects left the MPR. It said the 405-month figure represented ‘a 23% increase since second pass approval,’a milestone marking Defence’s green light for a contract to be
Already have an account? Log in
Want to keep reading this article?
More from Defence Notes
-
Spain unveils new multi-billion euro defence investment plan
The new plan outlined how Spain would reach 2% of its GDP spend on defence by 2025, with €1.9 billion earmarked for new equipment acquisition with several land, naval and air platforms disclosed to be replaced or upgraded.
-
New Zealand boosts defence spend to US$6.6 billion and vows increased closeness with Australia
This budget will be spent over the next four years and nearly doubles the country’s defence spending as part of GDP to 2%.
-
UK Chancellor commits £2 billion to make the country a “defence industrial superpower”
Rachel Reeves announced port upgrades, protected budgets for innovation and investment in novel technologies.
-
Avalon 2025: Australian defence budget meets the low expectations of show attendees
The Australian Budget was marked by tax cuts and a looming general election which led to little hope that there would be a substantial defence boost even with a big bill for nuclear submarines due.
-
Launch of Gilat Defense targets DoD market
The communications company Gilat launched its new Gilat Defense division at the Satellite 2025 expo, with future solutions aimed at US military customers.