Malaysia considers whether to stick or twist with LCS
The Malaysian Ministry of Defence (MINDEF) is mulling how to proceed with its troubled Maharaja Lela -class Littoral Combat Ship (LCS) programme.
None of the six LCS vessels on order from Boustead Naval Shipyard have been successfully completed, Defence Minister Datuk Seri Ismail Sabri Yaacob told parliament on 3 August.
LCS 1 is almost 60% completed, ahead of LCS 2 (48%), LCS 3 (43.75%), LCS 4 (36.49%) and LCS 5 (20%). Construction of LCS 6 is yet to begin.
This means that the overall programme is some 31 months behind schedule, Ismail Sabri said, and costs are spiralling beyond the original MYR9.13 billion ($2.16 billion) contract ceiling.
The LCS project faces a Cabinet-level review, with three options in play.
‘The first option is for the project to be continued by appointing Naval Group France as a rescue contractor… using the remaining contract ceiling to complete at least two LCS units,’ Ismail Sabri said.
Alternatively, Boustead Naval Shipyard would be required to complete ‘at least two LCS units’ within the remaining contract ceiling, he added.
The third option is to terminate the contract entirely, with the government stepping in the save the LCS programme.
Ismail Sabri said that saying that MINDEF does not intend to inject additional funds for Bousted Naval Shipyard to complete the LCS programme, despite a request from the shipbuilder.
However, the government could pay for the design rights and complete construction itself.
As part of our promise to deliver comprehensive coverage to our Defence Insight and Premium News subscribers, our curated defence news content provides the latest industry updates, contract awards and programme milestones.
Related Programmes in Defence Insight
Maharaja Lela Class [Malaysia]
Related Equipment in Defence Insight
More from Naval Warfare
-
Lockheed Martin strengthens Spanish SPY-7 radar supply chain
The global defence giant chose a Spanish firm for its work on the Bonifaz-class frigate.
-
Oostende mine countermeasures vessel begins sea trials
The first vessel in the Belgian-Dutch rMCM mine-clearing fleet, the Oostende, has begun its sea trials before officially entering service in 2025.
-
US Navy places $312 million contract with Textron Systems for landing craft
Textron’s latest order for Ship to Shore Connector (SSC), Landing Craft, Air Cushion (LCAC) follows on from a contract placed in August 2023 for five LCAC.
-
Japan to boost surface fleet with new destroyers and missile ships
Japan is enhancing its naval capabilities with the construction of the 13DDX advanced destroyer and Aegis System Equipped Vessels (AESV), aiming to strengthen its air and missile defence amid increasing security threats, particularly in East Asia.