New AMPV RFP updates development schedule
A final RfP has been released for the US Army’s Armored Multi-Purpose Vehicle (AMPV) requirement keeping the programme alive amid budgetary concerns.
The US Army’s TACOM procurement agency released the RfP on 26 November which laid out the latest requirements and funding levels for the programme that aims to replace the M113 family of vehicles.
An Engineering, Manufacturing and Development (EMD) phase is expected to last 54 months between FY2015-19.
The EMD contract award is expected in the first quarter of 2015 and funding for each year comprises: $70 million for FY15; $174 million in FY16; $114 million for FY17;
Our news & analysis is now part of Defence Insight®
A Basic-level or higher Defence Insight subscription is now required to view this content.
More from Land Warfare
-
NATO’s Crystal Arrow factors in Ukrainian UGV lessons as European interest grows
One goal of NATO’s Exercise Crystal Arrow was to identify the potential uses of uncrewed ground vehicles – as seen on the Ukrainian battlefield – and put platforms into the hands of users.
-
SOF Week 2026: Galvion unveils Cortex Evo integrated combat helmet
Galvion has introduced its Cortex Evo integrated head system, combining ballistic protection, power, data and processing capabilities within a single combat helmet architecture.
-
Why cost-effective flexible networks are the key to C-UAS success
The widespread use of drones and loitering munitions in current conflicts has tilted the balance in favour of the attacking force, both operationally and economically. EOS’s Dr Andreas Schwer tackles the question of what kind of C-UAS defences are needed to protect battlefield forces, and even entire countries.
-
The C-UAS challenge: Finding the threat before it finds you
How Teledyne FLIR Defense C-UAS solutions – and sensors optimized for third-party systems integrators – deliver early drone detection and decision advantage for UAS threat response