New AMPV RFP updates development schedule
A final RfP has been released for the US Army’s Armored Multi-Purpose Vehicle (AMPV) requirement keeping the programme alive amid budgetary concerns.
The US Army’s TACOM procurement agency released the RfP on 26 November which laid out the latest requirements and funding levels for the programme that aims to replace the M113 family of vehicles.
An Engineering, Manufacturing and Development (EMD) phase is expected to last 54 months between FY2015-19.
The EMD contract award is expected in the first quarter of 2015 and funding for each year comprises: $70 million for FY15; $174 million in FY16; $114 million for FY17;
Already have an account? Log in
Want to keep reading this article?
More from Land Warfare
-
IDEF 2025: Calidus targets more exports as Alhedah armoured 4×4 enters full production
The Alheda variant being shown at IDEF 2025 was the protected four-door version with a flatbed at the rear which is known to have been supplied to Ethiopia.
-
IDEF 2025: Aselsan shows new counter-drone systems
Korkut 130/25 SB is a four-wheeled trailer-mounted system and the second is the Korkut 100/25 SB which is fitted with similar equipment to the trailer system.
-
Czech Government increases Leopard tank ties
The Czech Government is aligning itself even more closely to a future fleet of Leopard tanks as other countries in Europe also sign up for the Leopard 2A8 variant.