Challenger 3 upgrade includes three phases but ammo requirements remain unclear
Challenger 2 MBT demonstrator armed with latest Rheinmetall 120mm L55A1 smoothbore gun plus new Thales commanders and gunner's stabilised sights. (Photo: RBSL)
RBSL (a JV between Rheinmetall and BAE Systems Land) has confirmed that the British Army’s Challenger 3 MBT Life Extension Programme (LEP) will comprise three phases with an expected in-service date of 2027.
The first phase, now underway, covers the building of six pre-series Challenger 3 MBTs at the RBSL facility in Telford.
This will be followed by Phase 2 LRIP of a further 18 units, with Phase 3 being full-rate production of 203 tanks.
The end result will be sufficient to equip two regiments of the Royal Armoured Corps (RAC) plus vehicles for training and reserve.
There
Our news & analysis is now part of Defence Insight®
A Basic-level or higher Defence Insight subscription is now required to view this content.
More from Land Warfare
-
Eurosatory 2026: IDV expands with new Viking and CL2X UGV
At Eurosatory 2026, uncrewed ground vehicles (UGVs) are front and centre of IDV’s display, with a new variant of the Viking and the new CL2X on show.
-
Eurosatory 2026: Robots rule as large and wheeled systems with articulated legs stand out
Dozens of uncrewed ground vehicles have been on display at Eurosatory 2026, with particularly notable platforms including VisionWave's Varan and Patria's planned uncrewed TRACKX.
-
Eurosatory 2026: AM General’s Hawkeye gains traction as JLTV A2 targets 2027 FRP
AM General’s Hawkeye adds a howitzer to a light vehicle as the company highlights strong interest in the system following an order from Kosovo, with demonstrations scheduled for a dozen countries.