Elderly USN submarine tenders to serve for another decade
USS Emory S. Land pictured after completion of its scheduled maintenance availability refit in April 2021. (Photo: Mrityunjoy Mazumdar)
In early April, the USN submarine tender USS Emory S. Land (AS 39) completed a $33.53 million scheduled maintenance availability refit lasting more than seven months at the Mare Island Dry Dock Company in Vallejo, California.
The vessel emerged from the dry dock in March 2021 and departed Vallejo on 7 April 2021.
In all, the ship spent 80 days longer than planned at Mare Island, partly because of COVID-related restrictions on dockyard working practices as well as additional work packages.
The scope of the work included scheduled regular overhaul and corrective maintenance of numerous shipboard systems, including electrical
Our news & analysis is now part of Defence Insight®
A Basic-level or higher Defence Insight subscription is now required to view this content.
More from Naval Warfare
-
Lessons shaping the next phase of Arleigh Burke production post-Flight IIA
The accelerated delivery of the final Flight IIA destroyer, USS Patrick Gallagher, showcases the payoff of years of workforce investment and process reform at Bath Iron Works, with the lessons feeding into Flight III production.
-
Ukraine war drives ‘minimum deployable capability’ doctrine in uncrewed systems development
Ukraine’s battlefield has rewritten the rules of uncrewed systems development. For Syos Aerospace, real-time operator feedback, lean serial production and a system-of-systems philosophy are central to its operating model.
-
Peru partnership may serve as a template for South Korean naval exports into South America
With a growing pipeline of naval modernisation programmes in South America, South Korean companies could be set to expand their presence in the region as recent contract wins highlight growing collaboration.