F-35B delivery date slips to 2026, UK MoD confirms
The seven F-35B aircraft in Lot 17 should have been delivered by 2025. (Photo: Crown Copyright)
Delivery for four out of the remaining seven aircraft in the UK’s initial order of F-35B combat jets has slipped to next year, the UK Ministry of Defence (MoD) has said.
The aircraft, which were all originally set to be delivered at the end of 2025 as part of production contract Lot 17, now won’t be delivered until April 2026 – three to four months outside of the original contract. Three F-35B aircraft are still set to arrive on schedule.
Responding to questions in the UK Parliament, UK defence minister Luke Pollard said that despite this delay it is “not expected to have an
Our news & analysis is now part of Defence Insight®
A Basic-level or higher Defence Insight subscription is now required to view this content.
More from Air Warfare
-
Saab shows uncrewed concept and accelerates programme with first flight due in 2027
Saab expects to fly two collaborative combat aircraft demonstrators, A1 and A2, before the end of the decade, but has stressed that the A3-001 mock-up unveiled on 21 August is only a concept for what could follow in the 2030s.
-
GKN Aerospace begins engine tests for drone design as part of contract signed in November
A mock-up displayed by GKN Aerospace on 21 August is planned to have a maximum range between 600km and more than 1,000 km with a payload capacity of 100-300kg.
-
Pentagon’s 800% PAC-3 MSE surge faces production bottleneck as Patriot demand soars
The Pentagon wants to procure 3,203 PAC-3 MSE interceptors in FY2027, but production constraints and international demand could impact efforts to rebuild depleted missile stocks.